The process of loading 177 fuel assemblies into the core of unit 2 at China's Zhangzhou nuclear power plant has begun, as announced by China National Nuclear Corporation.
Unit 2 is the second of four Hualong One (HPR1000) reactors under construction at the site.
China's Ministry of Ecology and Environment issued an operating licence for Zhangzhou Nuclear Power Unit 2 on 11 October.
Dong Baotong, Vice Minister of Ecology and Environment and Director of the National Nuclear Safety Administration, issued a licence to Zhangzhou Energy.
Zhang Kai, member of the Party Group and Deputy General Manager of China National Nuclear Corporation (CNNC), attended the event.
At 16:13 on the same day, workers began to load the first reactor nuclear fuel into Zhangzhou 2.
Author's summary: Fuel loading started at Zhangzhou unit 2.