The Morgantown Utility Board (MUB) is shifting its attention to the lower portion of Popenoe Run, with the upper restoration project largely complete.
MUB approved a $72,000 task order for Thrasher Group to develop a preliminary engineering report and hydraulic study of the area.
Thrasher will evaluate the condition of the existing stormwater system from the WVU Alumni Center Pond – and even do some evaluation upstream as far as the hydraulic analysis goes – down Patteson Drive and into Krepps Park, and recommend project alternatives
Said MUB General Manager Mike McNulty.
Author's summary: MUB shifts focus to Popenoe Run's lower portion.